From Sample to Mass Production: A Realistic OEM Timeline

Scoping, design, prototype, pre-compliance, certification, tooling and ramp - what each stage actually takes.

The stages and their typical windows

Scoping 1-2 weeks; industrial design 4-8 weeks; electronics and prototype 4-8 weeks; pre-compliance 2-4 weeks; certification 4-10 weeks; tooling and ramp 4-8 weeks; mass production 4-6 weeks. For sensor products based on an existing core board, a full programme commonly lands in the 6-9 month range. Programmes that skip pre-compliance usually lose more time at the lab than they saved.

What compresses the schedule

Reusing a validated core board, fixing the target market and certification route at scoping, signing off appearance samples in one round, and preparing packaging artwork in parallel with electronics validation. What does not compress the schedule is an external lab's queue - build that into the launch date.

What to ask for at each gate

A written feasibility view at scoping, appearance samples at design sign-off, working prototypes with a test summary, a pre-compliance report before lab submission, a certificate with a model-matched test report, and a pilot-run yield report before volume release.

Working on a sourcing programme? Our engineering and certification team replies with a written feasibility view within one business day. Send your requirement →

Related Articles

Ready to build your product line?

Send us the device type, target volume and launch market. Our engineering and certification team replies with a written feasibility view within one business day.